The much-anticipated tiling has started. Some prep work was needed in the master bathroom before the actual laying of tile, such as installing the bathtub and creating a shower base.
Bathtub Installed
Shower Base![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEh_TYd-WGPtv3nNUdsjVRdgzWc1yj8uRd32sFTnjYoQm6OIOMEtHOpI5lM5EUNJk-6JR-Qogouylf4VVfMs1jnLKy8uX7wWkXmlT3PQ19Sz2od2dWi0enHkR4Lppvv-q7HIXqf9DRyi-4k/s400/ShowerBaseSheetForTile.jpg)
Everything needed to be moved out of the great room and the bedrooms. A lot of it ended up stacked on the wood flooring.
Oak Floor As Storage Platform![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjcryZHhYRfs56-RJfhGX1j7ITTCmCjKuMfrjSGIwFqT_y4RJRlQLvPSRi96ThiQjnzb5UzsraTS3SeiF0fNPThyphenhyphenIE-5o94O6T5-wt6msJdJJbtJZs2UMXy7Qj3jDXCr5rH1dJHsXRViyA/s400/OakFloorAsStoragePlatform.JPG)
The bulk of the great room has been tiled with a porcelainized ceramic tile. The edges, where tile cutting is required, remain to be finished.
Great Room Tiled![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEgt4rH8pGCjK9roySQDwyKs9jOpxw1f2Oh9-DgtrOCBv5ASARFkUk3WuNCuxS2LN-2iM3uxxt7NYpGcT9eekWfY97yakQQLv_bd2P9dw7uvmS7Kki4pz1FIr0bR4_RYvIKcW9NGk0vkFxk/s400/GreatRoomTiled.JPG)
They were just starting to lay the tile in Pete's bedroom.
Pete's Room![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEhn8CkGHUOPNXtsK-gLBw76_xgLpjUEmUrRcVF41xg28HwKuxaWCWkMCg_0WkjR1k-291mWuo4LF3mBwE_PMs_7OVRo6hiUmFhzI0N8Br5JDt80ZKp4oaebobcskttb22DGrYL0hxN79Lw/s400/PeteBedroomTileStarted.jpg)
And another crew was installing the oak risers and treads on the stairs.
Oak Stairs![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjT2s-6K-dkjzVZhvFNpiTVfhAl-LHOk1m05Pz9uWz2BBH23Omc4SPwTKyBiP3SQZ-DUYDwqArEu97kQj9erjLsVrYED_ecBG3SsmJXPtCxIgTDboluS_5-NboWr-AcqGSJSWre-cJasDs/s400/OakGoingInOnStairs.JPG)
And they continue to work on getting the exterior of the Trombe walls smooth. Most recently they ground the high spots off. You can see the white dust on the shingles to the east of the upper level Trombe walls.
Trombe Wall Exterior